An asphalt resurfacing project has begun on Haggerty Road from Tyler to Ecorse Roads in Van Buren Township.
Wayne County said this involves 0.96 mile of hot mix asphalt cold milling and resurfacing, concrete pavement repairs, ADA ramps, signing and pavement markings. The work was scheduled to begin July 16 and to be complete in November.
During construction, motorists can expect lane closures, but two-way traffic will be maintained. Intermittent stoppages in traffic may be encountered. Increased traffic congestion will be experienced. There will be no weekend closures for this project.
Motorists are advised to use caution when driving through work zones.
For more information, call the 24-hour customer service center at 888 ROAD CREW or visit waynecounty.com .
- Previous story Nick Mockeridge named to Albion College Athletic Hall of Fame
- Next story Sumpter Township board tiff continues at July 10 regular meeting